Quantitative Modeling of Change Order Impacts on Cost and Time Overruns in Indonesian Toll Road Infrastructure Projects

Authors

DOI:

https://doi.org/10.26877/asset.v8i3.2425

Keywords:

Change order modeling, cost overrun, time overrun, toll road construction, construction phase performance

Abstract

Change Orders (COs) are a major challenge in toll road infrastructure projects, often causing cost and time overruns. This study aims to identify key CO drivers and quantify their impacts on project performance in Indonesian toll road projects. A mixed-methods approach was applied, involving qualitative interviews with 35 experts (project managers, consultants, contractors) and quantitative surveys from 75 respondents covering 20 projects implemented between 2015 and 2023. Data analysis employed descriptive statistics, multiple linear regression, correlation analysis, and hypothesis testing using SPSS. Results show that five significant factors, namely poor planning, technical design changes, discrepancies between plans and site conditions, delays in land acquisition, and inadequate stakeholder coordination, explain 94.5% of CO variation (R² = 0.945). COs accounted for 94.9% of cost overrun variation (R² = 0.949) and 93.6% of time overrun variation (R² = 0.936). Design changes most strongly affected cost overruns (β = 0.419), while land acquisition delays had the greatest effect on time overruns (β = 0.537). COs have interrelated effects on cost and time, requiring integrated management from initiation to closure. The findings provide engineering and policy implications for precise contract documentation, rigorous planning, and proactive risk management to mitigate CO-induced overruns.

Author Biographies

  • Hadi Sasmito, Mercu Buana University

    Master Program in Civil Engineering, Faculty of Engineering, Mercu Buana University, Jl. Meruya Selatan, Kembangan, Jakarta Barat 11650, Indonesia.

  • Mawardi Amin, Mercu Buana University

    Faculty of Engineering, Mercu Buana University, Jl. Meruya Selatan, Kembangan, Jakarta Barat 11650, Indonesia

References

[1] J. Irawan, “Analysis of the Delay in the Implementation of Toll Road Project Work,” Eduvest-Journal of Universal Studies, vol. 5, no. 2, pp. 1499–1508, 2025. https://doi.org/10.59188/eduvest.v5i2.1716

[2] P. P. Shrestha and R. Maharjan, "Effect of Change Orders on Cost and Schedule for Small Low-Bid Highway Contracts," American Society of Civil Engineers, 2019. https://doi.org/10.1061/(ASCE)LA.1943-4170.0000323

[3] T. Huo, H. Ren, W. Cai, G. Q. Shen, B. Liu, M. Zhu, and H. Wu, "Measurement and Dependence Analysis of Cost Overruns in Megatransport Infrastructure Projects: Case Study in Hong Kong," ASCE Journal of Construction Engineering and Management, 2018. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001444

[4] Z. Tenno and A. Suroso, "Analisis Faktor Penyebab CCO dan Pengaruhnya Terhadap Biaya Kontraktor Pada Proyek Jalan Tol," Jurnal Aplikasi Teknik Sipil, 2021.

[5] R. H. Assaad, M. O. Ahmed, I. H. El-adaway, and P. P. Shrestha, "Management of Change Orders in Infrastructure Transportation Projects," American Society of Civil Engineers, 2023. https://doi.org/10.1061/(ASCE)SC.1943-5576.0000640

[6] M. O. Ahmed, R. H. Assaad, I. H. El-Adaway, E. Echele, K. Govro, and J. Watson, “Administering change orders in highway projects,” Journal of Legal Affairs and Dispute Resolution in Engineering and Construction, vol. 14, no. 2, p. 05021010, 2022. https://doi.org/10.1061/(ASCE)LA.1943-4170.0000528

[7] M. Das, X. Tao, Y. Liu, and J. C. Cheng, “A blockchain-based integrated document management framework for construction applications,” Automation in Construction, vol. 133, p. 104001, 2022. https://doi.org/10.1016/j.autcon.2021.104001

[8] R. H. Assaad, M. O. Ahmed, I. H. El-adaway, and P. P. Shrestha, "Management of Change Orders in Infrastructure Transportation Projects," American Society of Civil Engineers, 2023. https://doi.org/10.1061/(ASCE)SC.1943-5576.0000640

[9]` A. Klarin and Q. Xiao, “Automation in architecture, engineering and construction: a scientometric analysis and implications for management,” Engineering, Construction and Architectural Management, vol. 31, no. 8, pp. 3308–3334, 2024. https://doi.org/10.1108/ECAM-08-2022-0770

[10] A. Al Maamari and F. Khan, “Evaluating the causes and impact of change orders on construction projects performance in Oman,” International Journal of Research in Entrepreneurship & Business Studies, vol. 2, no. 1, pp. 41–50, 2021. https://doi.org/10.47259/ijrebs.215

[11] I. M. N. Sahid, G. S. Mulyono, A. Rianto, and F. A. Prambudi, "Influence Factors of the Implementation of CCO in Cost Overrun in Road Construction Projects in Klaten Regency," International Journal of Engineering Research and Applications, vol. 12, no. 3, pp. 45–51, 2022.

[12] K. K. Naji, M. Gunduz, and A. F. Naser, “The effect of change-order management factors on construction project success: a structural equation modeling approach,” Journal of Construction Engineering and Management, vol. 148, no. 9, p. 04022085, 2022. https://doi.org/10.1061/(ASCE)CO.1943-7862.0002350

[13] A. Y. Martanti, T. P. Kasih, and F. H. Tanojo, "Study of Variation Orders and Its Impact on Project Performance in Terms of Cost and Implementation Time in The Tenjoresmi Area Arrangement Project," Asian Journal of Engineering, Social and Health, 2024.

[14] O. I. Akinradewo, C. O. Aigbavboa, C. C. Okafor, A. E. Oke, and D. W. Thwala, “A review of the impact of construction automation and robotics on project delivery,” in IOP Conference Series: Materials Science and Engineering, vol. 1107, no. 1, p. 012011, Apr. 2021. https://doi.org/10.1088/1757-899X/1107/1/012011

[15] S. Al-Gahtani, “Review current value engineering studies towards improve automation within building information management (BIM),” International Journal of Civil Engineering, vol. 9, no. 2, pp. 1–9, 2022. https://doi.org/10.14445/23488352/IJCE-V9I2P101

[16] P. P. Shrestha and R. Maharjan, "Effect of Change Orders on Cost and Schedule for Small Low-Bid Highway Contracts," ASCE Journal of Construction Engineering and Management, 2019. https://doi.org/10.1061/(ASCE)LA.1943-4170.0000323

[17] M. Williams, "Factors Leading to Time Overrun in Road Construction Projects," Journal of Civil Engineering, vol. 44, no. 1, pp. 25–32, 2016.

[18] B. Hwang, X. Zhao, and S. P. Low, "Impact of Time Overrun on Quality and Cost in Infrastructure Projects," Construction Management and Economics, vol. 39, no. 2, pp. 101–115, 2021.

[19] P. C. Anastasopoulos and A. B. Whitford, "The Role of Change Orders in Highway Construction: A Case Study Approach," Transportation Research Record, vol. 2673, no. 2, pp. 205–214, 2019.

[20] X. Zhao, et al., "Loss of Trust Due to Project Delays: The Case of Indonesian Toll Roads," Journal of Project Management, vol. 5, no. 1, pp. 33–41, 2019.

[21] S. O. Ogunlana, "Environmental Impact of Construction Delays in Toll Road Projects," International Journal of Construction Management, vol. 18, no. 1, pp. 55–62, 2018.

[22] D. O. Aghimien, C. O. Aigbavboa, A. E. Oke, and W. D. Thwala, “Mapping out research focus for robotics and automation research in construction-related studies: A bibliometric approach,” Journal of Engineering, Design and Technology, vol. 18, no. 5, pp. 1063–1079, 2020. https://doi.org/10.1108/JEDT-09-2019-0237

[23] A. G. Abdelwahab and T. S. El-Mikawy, "Risk Assessment for Change Orders in Highway Construction Projects," International Journal of Project Management, vol. 40, no. 1, pp. 75–86, 2022. https://doi.org/10.1061/(ASCE)LA.1943-4170.0000528

[24] M. Parsamehr, U. S. Perera, T. C. Dodanwala, P. Perera, and R. Ruparathna, “A review of construction management challenges and BIM-based solutions: perspectives from the schedule, cost, quality, and safety management,” Asian Journal of Civil Engineering, vol. 24, no. 1, pp. 353–389, 2023. https://doi.org/10.1007/s42107-022-00501-4

[25] Y. Pan and L. Zhang, “Roles of artificial intelligence in construction engineering and management: A critical review and future trends,” Automation in Construction, vol. 122, p. 103517, 2021. https://doi.org/10.1016/j.autcon.2020.103517

Downloads

Published

2026-06-06

Issue

Section

Articles